CEMENT INDUSTRY
Plant Renovation / Rehabilitation Contracts
| NO |
CLIENT’S NAME |
SCOPE AND LOCATION OF THE CONTRACT |
DATE/WORKS COMMENCED |
DATE WORKS COMPLETED |
|
1. |
ÇİMSA CEMENT FACTORY |
Mechanical and Rehabilitational Fabrication/erection Works for the Production line II MERSİN |
05.01.2000 |
18.04.2000 |
|
2. |
YİBİTAŞ LAFARGECOPPE ANATOLIAN CEMENT INDUSTRY AND TRADING CO. |
Revision of Rotary Kilns No I and II. Of Sivas Cement Factory SİVAS |
28.01.1997 |
15.04.1997 |
|
.3. |
SET ANKARA CEMENT FACTORY |
Revision of the Rotary Kiln ANKARA |
01.04.1994 |
15.05.1994 |
| 4. |
Ankara Cement Factory |
Manufacture and Replacement of the Kiln Gearbox ANKARA |
30.04.1991 |
30.07.1991 |
| 5. |
Bolu Cement Factory |
Revision of the Rotary Kiln BOLU |
15.02.1991 |
31.03.1991 |
| 6. |
Adana Cement Plant |
Revision of the Rotary Kiln ADANA |
30.05.1990 |
30.07.1990 |
| 7. |
Ünye Cement Factory |
Reconstruction of the Cooler of the Rotary Kiln ÜNYE |
23.11.1987 |
06.06.1988 |
| 8. |
Adana Cement Plant |
Revision of the Rotary Kiln ADANA |
30.04.1988 |
15.06.1988 |
| 9. |
Ünye Cement Factory |
Replacement of Rotary Kiln Shell Parts ÜNYE |
23.03.1986 |
23.04.1986 |
| 10. |
ÇİMSA CEMENT FACTORY |
Replacement of the Rotary Kiln Ring MERSİN |
19.11.1984 |
19.12.1984 |