CEMENT INDUSTRY
Auxillary Works Projects
|
NO |
CLIENT’S NAME |
SCOPE AND LOCATION OF THE CONTRACT |
DATE/WORKS COMMENCED |
DATE WORKS COMPLETED |
|
1. |
Supply and Erection of Two Steel Dome Structures for Raw Material Storage MERSİN |
01.07.1998 |
15.03.1999 |
|
|
2. |
Manufacturing and Erection Works for Rehabilitation of Cement Grinding Plant MARDİN |
27.04.1998 |
15.02.1999 |
|
| 3. |
Design and Manufacturing Works of a Gas Conditioning Tower at Ünye Factory. ORDU |
30.06.1987 |
30.06.1988 |
|
|
4. |
KHD-ASMAŞ |
Fabrication and Erection Works of Adana Cement Plant ADANA/TURKEY |
14.05.1986 |
30.06.1987 |
| 5. |
General Directorate of Cement Industries |
Fabrication and Erection of Coal Preparation Facility for Ergani Cement Plant ERGANİ |
24.04.1987 |
01.02.1988 |
| 6. |
Çorum Cement Factory |
Fabrication and Erection of Silo Boiling & Pneumatic Transport System ÇORUM |
30.12.1986 |
21.06.1987 |